The Transportation Advisory Committee (TAC) as of 10/3/22
The TAC approved a Multi-Year (5 Years) Implementation Project Plan and recommended approval to the Board of County Commissioners. These items have been organized by the TAC as an effort to be get the county ready in the event the Walton Referendum passes in the upcoming 2022 General Election.
The TAC has been meeting since March of this year monthly to organize and prioritize transportation projects for the community. This is a committee of our neighbors working to make Walton Wonderful.
The approved Capital Projects List can be viewed by CLICKING HERE.
Dollar Amounts Shown are in Today’s Dollars.
Freeport Capital Projects List Breakout
2023 Proposed
Project No | Project Name | Phase | Cost |
1A | Marquis Way West Extension | Design | $1,167,145 |
1B | Marquis Way | Design | $40,954 |
1C | Shipyard Rd (CR 83A E to Marquis) | Design | $100,792 |
4 | SR20 & US 331 Intersection Improvements | 50% Match (PD&E/PE/ROW/Construction) | $699,180 |
5 | SR20 (King Road to Black Creek | 50% Match (Design/ROW/Construction) | $4,850,000 |
18 | Marquis Way East Extension | Design | $966,059 |
2024 Proposed
Project No | Project Name | Phase | Cost |
1A | Marquis Way West Extension | CEI/Construction | $4,668,580 |
1B | Marquis Way | CEI/Construction | $163,814 |
1C | Shipyard Rd (CR 83A E to Marquis) | CEI/Construction | $403,168 |
4 | SR20 & US 331 Intersection Improvements | 50% Match (PD&E/PE/ROW/Construction) | $759,979 |
5 | SR20 (King Road to Black Creek) | 50% Match (Design/ROW/Construction) | $35,100,000 |
21 | Blue Ridge Parkway Improvements | PD&E and/or PE | $59,787 |
25 | Marquis Way East Extension | CEI/Construction | $3,864,238 |
27 | Freeport East Connector | PD&E and/or PE | $298,321 |
2025 Proposed
Project No | Project Name | Phase | Cost |
1 | R20 & US 331 Intersection Improvements | 50% Match (PD&E/PE/ROW/Construction) | $1,747,951 |
2 | SR20 (King Road to Black Creek) | 50% Match (Design/ROW/Construction) | $34,960,000 |
8 | Blue Ridge Parkway Improvements | ROW Acquisition | $597,866 |
11 | Freeport East Connector | ROW Acquisition | $2,953,207 |
2026 Proposed
Project No | Project Name | Phase | Cost |
1 | SR20 (King Road to Black Creek) | 50% Match (Design/ROW/Construction) | $34,960,000 |
5 | Blue Ridge Parkway Improvements | Design | $338,791 |
6 | Freeport East Connector | Design | $1,673,484 |
13 | North Freeport Connector | PD&E and/or PE | $205,440 |
17 | Business 331 | Design | $390,957 |
2027 Proposed
Project No | Project Name | Phase | Cost |
4 | North Freeport Connector | ROW Acquisition | $2,054,405 |

From the “Identified Transportation Projects” list and Does not Directly Correlate to the Capital Projects List used above. What we can connect is listed below.
Capital Projects List | Image Item |
1A Marquis Way West Extension | 22 |
1B Marquis Way | 23 |
1C Shipyard Rd (CR 83A E to Marquis) | 21 |
18 Marquis Way East Extension | 24 |
5 Blue Ridge Parkway Improvements | 18 |
27 Freeport East Connector | 25 |
13 North Freeport Connector | 26 |
17 Business 331 | 11 |
Phase Explanations as best understood;
Initial Phase – May vary depending on the project.
– PE = Preliminary Engineering
– PD&E = Project, Development, & Engineering
ROW = Right of Way Acquisition
Design = Design
CEI / Construction = Construction, Engineering, Inspection / Construction
– the way we understand it is that a project may or may not have the CEI component depending on the size and requirements. CEI is essentially an accountability layer withing the Construction phase.
Totals
5 Years
10 Projects
Investment Amount = $133,024,118.00
In Closing
We’re very excited to see further details and expectations set around the Walton Referendum! This looks like a very positive list of projects! Which project are you most excited about? If you ask us, we vote the Marquis Project connected the community of Bay Loop/ Hammock Bay to 331 as an alternate to Highway 20 – very cool!